Name of Project: Construction of 20 kV overhead line (OHL) from Gledachevo S-st to movable substation in Troyanovo-1 Mine
   
Contractor: Mini Maritsa Iztok EAD, Radnevo
   
Description:

Construction of new 20 kV OHL is necessary to power supply movable substations and mine consumers in Maritsa Iztok Mines, Radnevo.

The OHL passes along a newly designed route. Connection on one side is aerial with 20 kV Switchgear of Gledachevo S-st, and on the other side there will be cable connection with the end consumer. Entire length of the OHL is 6 km. Scope of the contract includes supply and installation of all the equipment necessary for implementation of the order.

   
Date of Assignation: 03.2016
   
 Activities:
   
Other: