Name of Project: Electrical installation works - 2nd stage - for integration of 110/20 kV Substation "Proslav" (Plovdiv) to Bulgarian electrical power system
   
Contractor: National Electric Company (NEC) EAD "Trafoelektroinvest" State Enterprise, Sofia
   
Description: This order was assigned to EL KONTROL by the National Electric Company (NEC) EAD "Trafoelektroinvest" State Enterprise, Sofia in January 2005. Substation "Proslav" project concerns erection of a new 110/20 kV Substation in the town of Plovdiv, and its integration to the Bulgarian electrical power system. The order awarded to EL KONTROL includes electrical installation works in 110 kV Switchyard, as listed below:
   
Lead in exploitation: 2007
   
Finished Activities:
▪ Substitution of 110 kV equipment – circuit breakers, disconnectors, power and voltage measuring transformers, surge arresters, supporting insulators;
▪ Laying and connection of 20 kV power cables;
▪ laying and connection of control cables;
▪ Installation of tubular busbar system in 110 kV Switchyard;
▪ Installation, commissioning and preparation of executive documentation for spare relay protection;
▪ Control tests and commissioning of the installed equipment.
   
Other: A reference has been issued by NEC EAD - Trafoelektroinvest State Enterprise as a proof for the prompt implementation of these orders.