Name of Project: Electrification of ID fan of Unit 7 - primary and secondary commutation
   
Contractor: NEC EAD Electricity Distribution Enterprise, Stara Zagora
   
Description: Electrification of ID fan of Unit 7 – primary and secondary commutation. The order has been assigned by NEC-EAD Electricity Distribution Enterprise, Stara Zagora.
   
Lead in exploitation: 1999
   
Finished Activities:
▪ Laying, connection by cable terminals and electrical testing of 6 kV power cable;
▪ Laying, testing and connection of control cables;
▪ Equipment and commissioning 6 kV cubicles for electrifying fume-gas ventilator.
   
Other: