Name of Project: Erection of trade measuring of electrical power consumed by Kaproni Plc., Kazanlak
   
Contractor: National Electric Company EAD
   
Description: Order concerns erection of trade measuring of the electrical power consumed by six 20 kV cable transmission lines. Practically by erection of this new system the existing measuring systems are being modernized and consolidated. The order includes overall engineering of the measuring system (design, supply and installation) by observation of all the requirements of the Department for measuring, reporting and control of electrical energy (MRCE) relevant to NEC. Through the new system the MRCE Department of NEC is reported for the consumption of electrical energy on remote bases through GPRS modem.
   
Lead in exploitation: 2008
   
Finished Activities:
▪ Design of project for remake and operating of the existing measuring systems;
▪ Delivery of current transformers, voltage transformers, manufacturing of a cabinet for electrical measuring;
▪ Installation of current transformers, voltage transformers and a cabinet for electrical measuring;
▪ Control tests and commissioning of the erected equipment.
   
Other: