Name of Project: Delivery and retrofit of 6kv Circuit Breakers (CBs), design of project for installation of CBs and installation of two CBs
   
Contractor: Toploficatsia - Rousse AD
   
Description: The order presents part of the repair programme of Toploficatsia - Rousse for year 2009
   
Lead in exploitation: 2009
   
Finished Activities:
▪ Delivery of vacuum Circuit Breakers AREVA;
▪ Design of project for retrofit of carriers and replacement of CBs;
▪ Retrofit of 2 carriers and assembly of 2 CBs;
▪ High-voltage control tests, commissioning, issue of certificates for operational tests.
   