Name of Project: Supply and erection of lighting system in Buffer pond Area of Enel Maritsa East 3 Power Plant
   
Contractor: ENEL Produzione S.p.A. - Branch Bulgaria
   
Description: This order represents part of the rehabilitation project of Enel Maritsa East 3 Power Plant
   
Lead in exploitation: 2009
   
Finished Activities:
▪ Supply of materials for erection of lighting system;
▪ Design, manufacturing and installation of power distribution panels;
▪ Erection of lighting system, laying and connection of power cables;
▪ Commissioning works.
   