El Kontrol - Beginning
 
 
Name of Project: Substitution of electrical drives in 110 kV Outdoor Switchgear in Maritsa East 2 TPP
   
Contractor: NEC EAD Electricity Distribution Enterprise, Stara Zagora
   
Description: Substitution of electrical drives in 110 kV Outdoor Switchgear in Maritsa East 2 TPP. The order has been assigned by NEC EAD Electricity Distribution Enterprise, Stara Zagora.
   
Lead in exploitation: 2000
   
Finished Activities:
▪ Installation of electromotor movements;
▪ Laying, testing and connection of control cables
▪ Centering adjustment of knife disconnectors.
   
Other: