El Kontrol - Beginning
 
 
Name of Project: Reconstruction of 110/6.3 kV substation No 2B
   
Contractor: Mini Maritsa Iztok EAD
   
Description: 110 кV Open-yard switchgear – primary commutation; Erection of local, emergency and security lighting of 110 кV Open-yard switchgear; Delivery and Installation of new sections for 6,3 кV Indoor switchgear-1 and 6,3 кV Indoor switchgear-2 – primary commutation, earthing system, a battery, a stabilized rectifier, AC and DC auxiliary panels; auxiliary installations - lighting and power; secondary commutation.
   
Lead in exploitation: 03.2012
   
Finished Activities:
110 кV Open-yard switchgear – primary commutation; Erection of local, emergency and security lighting of 110 кV Open-yard switchgear; Delivery and Installation of new sections for 6,3 кV Indoor switchgear-1 and 6,3 кV Indoor switchgear-2 – primary commutation, earthing system, a battery, a stabilized rectifier, AC and DC auxiliary panels; auxiliary installations - lighting and power; secondary commutation.
   
Other: