Name of Project: Erection of 20/6/0,4 kV Movable Substation "Staroselec"
   
Contractor: Mini Maritsa Iztok EAD
   
Description: This order has been assigned to EL KONTROL by Maritsa East Mines and it concerns erection of 20/6/0,4 kV movable substation. Such kind of Substation has been needed to answer the specific requirements of the non-stationary mine-extraction activity.
   
Lead in exploitation: 2002
   
Finished Activities:
▪ Installation of power transformers;
▪ Installation of 20 kV and 6 kV switchgears (movable type);
▪ Laying of power and control cables;
▪ Erection of earthing and lightning-protective installations;
▪ Control measurements;
▪ Tests and commissioning of the power equipment.
   