El Kontrol - Beginning
 
 
Maritsa East 3 TPP
Project:
Repair of transformers of Unit 1, Unit 2, Unit 3, and Unit 4 at Contour Global Maritsa East 3 TPP

Contractor:
Contour Global Maritsa East 3 AD

Statute:
implemented /2015

project implemented current


Project:
Maintenance of lighting installations in Contour Global Maritsa East 3 TPP

Contractor:
Contour Global Maritsa East 3 AD

Statute:
implemented /2015

project implemented current


Project:
Disassembly, design, installation and commissioning of electrical and C & I equipment in Coal Handling Plant at Enel Maritsa East 3 TPP

Contractor:
Enel Maritsa East 3 AD

Statute:
implemented /2011

project implemented current


Project:
Reconstruction and extension of 400 кV Outdoor Switchgear in Maritsa East 3 TPP as a part of a 400 кV power distribution line from Maritsa East 3 TPP to substation "Alibeikjoi" (Turkey)

Contractor:
NEC EAD Trafoelektroinvest State Enterprise

Statute:
implemented /2003

project implemented current


Project:
Rehabilitation of Power Unit 2 of Maritsa East 3 TPP

Contractor:
Consortium DSD Dillinger Stahlbau GmbH / RWE Industrie-Losungen GmbH

Statute:
implemented /2006

project implemented current


Project:
Rehabilitation of 220 kV Switchgear at Maritsa East 3 TPP - second stage: Substitution of disconnectors and circuit breakers

Contractor:
The National Electric Company (NEC) EAD High Voltage Network Enterprise, Sofia

Statute:
implemented /2004

project implemented current


Project:
Erection of cable trays and laying of power cables for electrifying FGD Plant for Units 1, 2, 3 and 4 of Maritsa East 3 TPP

Contractor:
Siemens Sanayi ve Ticaret A. S - Turkey

Statute:
implemented /2006

project implemented current


Project:
Rehabilitation of Maritsa East III - Unit 1

Contractor:
ENEL Produzione S.p.A. - Branch Bulgaria

Statute:
implemented /2007

project implemented current


Project:
Maritsa East 3 TPP - Rehabilitation of Unit 4

Contractor:
NEC EAD "Тrafoelectroinvest" Enterprise, Sofia

Statute:
implemented /2009

project implemented current


Project:
Supply and erection of lighting system in Buffer pond Area of Enel Maritsa East 3 Power Plant

Contractor:
ENEL Produzione S.p.A. - Branch Bulgaria

Statute:
implemented /2009

project implemented current


Project:
Delivery of electrical equipment, design and installation works related to integration of Fire Fighting System to Fuel Oil Plant and Coal Handling Plant of Enel Maritsa East 3 TPP

Contractor:
E & Z Industrie-Losungen GmbH

Statute:
implemented /2009

project implemented current


Project:
Rehabilitation of Units 3 and 4 in Maritsa East 3 TPP - scope electrical works

Contractor:
Enel Produzione S.p.A - Branch Bulgaria

Statute:
implemented /2009

project implemented current


Project:
Design, erection and commissioning of C&I and electrical equipment in Coal Handling Plant, Enel Maritsa East 3 TPP

Contractor:
Enel Maritsa East 3 AD

Statute:
implemented /2009

project implemented current


Project:
Manufacturing, engineering, erection and set-up of cabinets and panels with relay protection for 220кV and 400кV Switchgears of The National Electric Company

Contractor:
Contractor: El-Test Ltd., Client: National Electric Company EAD

Statute:
implemented /2009

project implemented current