We completed rehabilitation of 110 kV Switchyard in 400/220/110/31.5 kV S/st Plovdiv

In September 2022, EL KONTROL successfully completed the significant project for Reconstruction of 110 kV Switchyard at the 400/220/110/31.5 kV Substation Plovdiv.

Project is part of ESO EAD's investment program and was started in May 2021. A wide range of activities were carried out - supply of equipment, construction and electrical installation works, commissioning works. 

We manufactured control and relay panels, control cabinets, power supply panels, metering cabinets, telecommunication cabinets, and installed them in the 110 kV Switchyard. 

This is the second project we have implemented at Plovdiv Substation after we completed electrical part of the 400 kV Switchyard in 2006. 

The Management of EL KONTROL would like to thank to every employee of the team for their professionalism and dedicated work. 