Project description

Scope of this project includes elaboration of a technical design for SCADA System and installation of SCADA System for eight railway stations, three Main Section Posts (MSP), and two Traction Substations (TS) situated along the railway lot Sofia – Kalotina-West.

In details, the assigned activities for SCADA installation include: delivery, installation, and wiring of equipment in electrical switchboards; establishing of surveillance and control connections; elaboration and set-up of software; start-up and commissioning of hardware and software; connection of panels to existing Ethernet network.

Монтираната SCADA система в тягова подстанция Волуяк 110/27 kV дава възможност за автоматично управление и наблюдение както от подстанцията, така и дистанционно, от Диспечерски център в София.

Activities

  • Elaboration of a technical design for SCADA;
  • Installation of SCADA System in 110/27 kV TS Voluyak;
  • Manufacturing and installation of PLC panels for surveillance and control of busbar sectionalizing switch, at the railway stations along the lot Sofia – Kalotina-West;
  • Installation of SCADA system in the Central Dispatch Center for surveillance and control of TS Voluyak, TS Aldomirovtsi, and the PLC panels in the railway stations.